Here is an update related to Project 8 & 9. Everything is weather contingent and barring any unforeseen issues
May 12: Mill Browning and Sanderson
May 13: Asphalt scratch course on Browning and Sanderson
On May 12 and 13 work on Browning will not start until after 8:00am to allow the bus traffic to clear.
It is anticipated that the work will be completed each day ahead of the bus traffic at 3:00.
May 16 and 17: Place asphalt base on Mettabrook
May 18, 19 and 20: Prepare driveway approaches on Mettabrook for concrete. The following week, Smith Paving to complete concrete placement.
May 19 and 20: Remove temporary concrete in Main Street road crossing and plate until asphalt is placed.