April 18- update Project 8 & 9 sewer separation

  • Writer: Shannon Shulters
    Shannon Shulters
  • Apr 18, 2022
  • 1 min read

W. Garfield roadwork is nearing completion. Curbs were installed, sidewalk and driveway approaches were dugout and concrete installation for them started last week. Contractor plans to start digging out Allen and West St starting the week of April 18 (weather contingent). This roadwork will not be as disturbing as W. Garfield so driveways will remain accessible during the work. There will be some exceptions such as when work is directly in front of the house but residents will be notified beforehand.